|
|

SPE-106610 Shafawi Removal
Mercury Removal System for Upstream Application: Experience in Treating Mercury
From Raw Condensate
Muhamad Rashid Sainal, Petronas Carigali Sdn. Bhd; Azman Shafawi, Petronas Research and Scientific Services Sdn.
Bhd.; and Ir. Abdul Jabar Mohamed, Petronas Carigali Sdn. Bhd.
Copyright 2007, Society of Petroleum Engineers
This paper was prepared for presentation at the 2007 SPE E&P Environmental and Safety
Conference held in Galveston, Texas, U.S.A., 5-7 March 2007.
This paper was selected for presentation by an SPE Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Society of Petroleum Engineers, its officers, or members. Papers presented at
SPE meetings are subject to publication review by Editorial Committees of the Society of
Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper
for commercial purposes without the written consent of the Society of Petroleum Engineers is
prohibited. Permission to reproduce in print is restricted to an abstract of not more than
300 words; illustrations may not be copied. The abstract must contain conspicuous
acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O.
Box 833836, Richardson, Texas 75083-3836 U.S.A., fax 01-972-952-9435.
Abstract
This paper presents an approach undertaken by PETRONAS
Carigali Sdn Bhd, an E&P subsidiary of PETRONAS in
selecting, optimizing and installing a mercury removal system
in one of its operations in Malaysia. It focuses on the treatment
of the raw condensate stream that was noted as having much
higher mercury content as compared to the gas stream. Since
the experience in mercury removal in raw condensate is
limited, this paper also presents the work done to mitigate the
risks and improve the removal performance. The paper shares
the initial performance of such system and the issues faced to
sustain its long term effectiveness.
Through operation surveillance, mercury was observed to be
present in the hydrocarbon delivered by PETRONAS Carigali
to its downstream customers. A Mercury Removal Project was
initiated in March 2005 to treat and remove the mercury from
the hydrocarbon. The Project was conducted on a fast track
basis. Adsorbent technology was selected following a
thorough evaluation that includes carrying out performance
tests in the laboratory. The project is among the first in the
world to remove mercury from raw condensates. (The gas was
not treated after the data established that the mercury content
in the gas meets specifications).
The project was completed in stages with the first system
installed in March 2006, and the second in July 2006. The
results show that the units managed to remove mercury from
the condensate with more than 95% efficiency. The project
demonstrated that the treatment of mercury could be done
upstream prior to exporting the hydrocarbon liquids. It is an
approach that should not be ruled out in the gas processing
value chain whether for reasons of risks mitigation or value
improvement or both.
Mercury is a natural occurring element and could be present in
varying concentrations and of various species in oil and gas
fields. Mercury is not only hazardous to human health and the
environment but could also attack equipment components that
have mercury reactive materials, leading to a potential
catastrophic failure to the plant.
Introduction
PETRONAS Carigali Sdn Bhd (PCSB) operates a network of
gas production facilities and infrastructure onshore and
offshore Terengganu, Malaysia. The main gas producing fields
are notably Duyong, Resak and Angsi, which produces both
crude oil and gas. The gas from Duyong and Resak are
delivered to shore via dedicated pipeline systems namely the
Joint Delivery System (JDS) and Resak Delivery system
(RDS, landing at the Onshore Gas Terminal (OGT) in Kertih,
Terengganu. Feeding into these delivery systems are also
supplies from other fields such as Sotong, Malong, Anding,
the PM-9 PSC fields and PM3 PSC. (The gas from Angsi field
is delivered to shore via a separate pipeline system operated by
others). Figure I shows the Gas Fields and the main pipeline
systems.

The gas and condensate delivered through these pipeline
systems are sent to the Gas Processing Plants (GPPs) which
are located nearby in the vicinity. The GPPs will process the
gas and condensate prior to sending the various products (sales
gas, ethane, butane, stabilised condensate etc.) to the various
Petrochemical Plants, Power Plants and downstream
consumers.
Historically since the first gas development and production in
the 1980's, the gas produced from those initial fields does not
require any treatment for contaminants. Offshore treatment
processes were mainly confined to dehydration and water
treatment systems. Though there were some contaminants
such as H2S, CO2 and trace elements present, they were very
minimal and required no further treatment to meet the gas
supply specifications. Similarly, the onshore facilities also
only consisted of mainly slugcatchers and custody transfer
metering systems prior to exporting the gas and condensate to
the GPPs. Nonetheless, continuous surveillance and checks
were conducted as part of routine operations to ensure
compliance to the quality specifications and HSE requirements
(33).
However, during recent years, elemental mercury was found in
vessels and piping low points of the gas production facilities.
Contaminants studies and data analysis were conducted for
both the RDS and JDS gas and condensate, in order to
ascertain the mercury level of both streams. The results show
that the mercury level in the gas stream was very minimal and
far below the specification. However, the raw condensate
stream contained a much higher level of mercury. A project
was initiated to remove mercury from the raw condensate
prior to delivering it to the GPPs and downstream consumer.
2.0 What is Mercury
2.1 Mercury in Oil and Gas industry
Knowledge of the total mercury content and of the different
species present in natural gas condensate is extremely
important. Mercury in most forms is highly toxic, particularly
when present as the organo-mercury species which causes
great environmental concern. In addition, the damage caused
to industrial plants by the presence of mercury can be severe
especially when unscheduled shut-downs are forced.
2.1.1 Mercury in Natural Gas Industry
Mercury occurs naturally, in trace quantities, in natural gas.
Although difficult to generalise, the typical mercury
concentration in natural gas/natural gas condensates is
between 1 and 200 ¦Ìg m -3 (1,2,3,4). Although the
concentration of mercury in natural gas and natural gas
condensates may be considered to be very low, the effect is
cumulative because it amalgamates. Mercury in natural gas
condensate may be present in various chemical states:
metallic, organic or inorganic forms, that all show unique
species-dependent physical, physiological and chemical
properties (1,5,6).
The implications from the presence of mercury in natural gas
was not reported until 1973, when a catastrophic failure of an
aluminium heat exchanger occurred at the Skikda liquefied
natural gas plant in Algeria (4, 7, 8, 9).
The presence of mercury in oil and gas is recognised world-
wide and has been reported for Gronigen field in Holland (8),
in Indonesia (10), in Thailand (9,11,12),in Malaysia(13,14),
fields in Australia (15), the Commonwealth of Independent
States (9,16), Western and Southern Africa, Chile and
Venezuela (17), Canada, in several states in the US (Kansas,
Texas, Utah, Colorado, Oklahoma, and Wyoming) (18,19), as
well as The Irish Sea, Japan and China (19).( Table 1)
2.1.2 Mercury in the Petrochemical Industry
As with the gas industry, several petrochemical companies,
using natural gas liquids containing mercury, have also had
some unfortunate experiences of damaging cryogenic heat
exchangers at their petrochemical complex (9,20,21). Other
petrochemical processes directly or indirectly utilise a catalyst
with precious metals such as platinum, palladium, nickel etc.
as an active surface. The presence of mercury in any stream of
a petrochemical process may easily poison the catalytic
process. (20, 22).
2.1.3 The Petroleum Industry and Environmental
Impacts from Mercury
Mercury is a naturally occurring contaminant in geological
hydrocarbons and is distributed freely throughout production,
processing, transportation and consumption systems. The toxic
contaminants from these activities can enter into the
environmental cycle and food chains easily, through emission
during processing stages or unregulated disposal of wastes or
accidents. As shown in Table I, hydrocarbons from different
geological locations contain mercury in microgram levels. The
values shown are estimations (23) and may change from time
to time, depending on geological factors and production
practices.

2.2 Determination of Mercury
The determination of mercury in natural gas and gas
condensates is made difficult by the very low concentrations
involved, the highly volatile nature of mercury and the
complexity of the sample matrix. This dictates that either a
highly sensitive detector or a large sample volume or both is
needed. A variety of techniques with different sensitivities are
presently available for the determination of mercury.
However, strict procedures including proper sampling
techniques have to be followed to ensure accuracy and
reproducible results. Some analytical techniques are listed in
Table II

An analyser for the determination of mercury in naphtha has
now been developed ie the NIC mercury analyzer (27), Leco,
Gallahard with precon system etc,. an atomization/oxidation,
traping/amalgamation and Cold Vapour Atomic Detection
principle is applied in this method. It has also been reported
that a rapid determination of total mercury in natural gas
condensates using vaporization/trap at elevated temperature on
gold amasil then thermally desorbed and detected by Cold
Vapour Atomic Fluorescence, gives satisfactory and consistent
results.(28)
2.3 Mercury speciation in natural gas Condensate
The determination of different mercury compounds, or
'speciation', in gas condensates is of interest not only because
of the ecotoxicological aspect but also because of the interest
in those problems associated with the processing, utilisation
and movement of gas condensate which contains mercury (6).
At present, it is not well known which chemical forms of
mercury are present in natural gases and gas condensates and,
in addition, methods for the determination of total mercury
concentrations must be regarded to be of unproven reliability
because of a lack of adequate standard reference materials and
poor accuracy (5).
In recent years, many methods have been developed for the
speciation of mercury in various types of samples. However,
there has been limited success with complex organic liquid
matrices due to the analytical challenges those samples offer.
The first attempt at speciation of mercury in gas condensates
(semi-quantitative determination) was performed using HPLC
coupled with CVAAS (6). Various mercury species in an
aqueous system were separated by reversed phase HPLC using
gradient elution to investigate the preliminary condition
required.
The determination of mercury species in gas condensates by
on-line amalgamation traps (gold/platinum wires) for the
collection of mercury species separated by capillary GC for
detection by MIP-AES was able to remove the carbon
background emission and allowed the determination of
dimethyl mercury in condensate. (25).
It also reported that speciation of mercury in condensate was
achieved by using GC-ICP-MS (29) and GC-Pyrolyser-AFS
(30). Several species of mercury i.e. elemental mercury,
mercury (II) chloride, DMM, methyl ethyl mercury (MEM)
and DEM were identified. However no organo-mercury halide
species were detected in the majority of samples analysed.
3.0 Mercury Data Surveillance and Analysis
A detailed data analysis was conducted based on the reports
and operational surveillance conducted by PCSB and
PETRONAS Research and Scientific Services (PRSS) from
year 2001 to 2005. Based on these analyses, the following was
concluded:-
- The mercury present in the gas streams for both RDS
and JDS are significantly below the gas sales
specification limits.
- Condensates have higher mercury content than gas.
Under normal operations, mercury loading ( kg / day
) to GPP in untreated condensate is 3 to 9 X higher
than that of gas.
- There is no specific trending (increasing or
decreasing with time) observed for both mercury in
gas and condensate.
- The condensate and gas stream from OGT are
delivered separately to GPP. At GPP, they are
commingled again in common inlet separators. As a
result of this commingling, it is highly likely that the
migration of mercury from the condensate stream
occurs to the gas stream resulting in increased
mercury content in the processed gas stream (34).
Based on the available data, it was recommended and agreed
to treat the condensate stream only for the time being.
However, continuous surveillance will be conducted for both
the gas and condensate streams to ensure conformance to
specifications.
4.0 Project Definition
A project called, "Mercury Removal Project 1 (MRP1) was
initiated in 2005 to remove mercury from the raw condensate.
Two locations were considered for the project, ie offshore
platform or onshore gas terminal. The followings highlighted
the considerations for both locations:-
Offshore Platform
- Potentially 8 - 12 vessels including pretreatment units
need to be installed per platform. This will impose
significant space and weight requirements on each
platform
- Structural modifications and extension need to be
conducted to accommodate the units
- Possibility of constructing new platforms or
extensions to accommodate the units. Though this is
possible, it will have a significant impact on the
schedule and cost
- More than one platform or location
Onshore Gas Terminal
- Availability of space for current units and further
future expansion
- Eliminate the immediate need for individual Mercury
Removal Unit on each offshore platform
- Faster project completion
- Lower overall costs due to logistics during project
and operation
- Avoid prolonged production shutdown leading to gas
supply interuption
Based on the above, it was decided that the Mercury Removal
System will be installed at the Onshore Gas Terminal.
4.1 Project Risks and Challenges
There were 2 major challenges identified during the project
definition.
- There was no Process Licensor with a track record in
removing mercury from raw and untreated
condensate. The short-listed / selected Vendors only
have proven experience in removing mercury in clean
"refinery-grade" condensate. Hence MRP1 will be
the 'pilot' project for both PETRONAS and the
vendor.
- Long lead time for the vessel plate and big size
valves could jeopardize the early completion of the
project. Vendor indicated about 32 to 34 weeks ex-
work for the delivery of the plate and about 24 to 32
weeks for valves with actuators (35).
4.2 Project Risk Management
The following initiatives were taken to mitigate and address
the project risks and challenges:-
- After a thorough technology selection process, a
performance testing of the absorbents with the actual
condensates were conducted. This gave some
indication on the performance of the absorbent in
'lab' condition.
- The MRU would be installed in 2 phases, ie the JDS
system and the RDS system. This would allow for the
monitoring of actual performance of JDS MRU, and
for any improvements to be made, if required, to the
RDS MRU later.
- Provide tie - in provision for future additional MRU
installation, if required.
- Conduct sourcing and source inspection for the long
lead items, ie vessel plate and big sized valves (35).
4.3 Technology Selection and Design
Considerations
There are many types of technology, proven and unproven,
currently available. Listed below are some of the available
technologies.
- Adsorbent
- Cyclonic
- Chemical
- Microbes & other emerging technologies (36)
The selection of the technology for the project was done as per
the following criteria and considerations.
- Proven and reliable technology
- The technology selected must be proven and
reliable on other types of process applications.
- Process effectiveness and efficiency
- The removal agent must be highly active towards
all forms of Hg, preferably bonding irreversibly
to the agent.
- The removal agent must also remain active, ie
the active surface must be resistant to blinding by
components in the stream treated.
- The system should also be flexible on demanding
feedstock properties.
- Lower resident time preferred. This will have an
impact on the sizing of the vessels.
- Stable and robust (physically and chemically).
- Ability to integrate with existing facilities
- Minimal modification to the existing facilities.
- Used commercially
- Removal agent should be inexpensive and easy
to get.
- Meeting the design basis.
- Ability of the technology to meet the design
basis.
- Time Constraint
- Ability for the technology and the facilities to be
4.4 Adsorbent Performance Test and Lab
Analysis
Mercury removal systems for both gas and processed liquid
hydrocarbon streams are commercially available. However,
removal systems for raw natural gas condensates have not
been sufficiently tested under real plant conditions.
The removal of mercury from raw natural gas condensates is
different to that from natural gas because it is in the liquid
phase and the types of mercury present in the condensate may
be of a different species. At present, few technologies are said
to be effective in the total removal of mercury from liquid
hydrocarbon feeds. There are several manufacturers, but most
of the products are not well tested for mercury removal from
actual 'raw' condensates. An example of such removal
systems includes the sulphide-containing ion exchange resin
material (20) comprising the two-stage sulphide-containing
alumina process (1, 31, 32), sulphur-containing molecular
sieve, sulphur-containing activated carbon and ionic salt -
containing activated carbon. In view of this, the performance
test using the real sample to confirm the performance of the
adsorbent becomes very important.
4.4.1 The Performance Evaluation of Removal
Adsorbent
The laboratory scale assessment of short-listed mercury
removal adsorbent systems, in removing mercury, particularly
alkyl mercury species ie DMM and DEM from actual samples
from OGT is very important in deciding the most suitable
system for the raw gas condensate.
The picture of the laboratory scale pilot plant used in the study
is shown in Figure II.
4.4.2 Determination of Total and Mercury Species
in Samples
The determination of the total mercury content in the inlet and
outlet samples was carried out using the vaporisation and
trapping technique (28) and that of the mercury species in the
samples was carried out using gas chromatography coupled
with pyrolysis-AFS respectively (30). The set-up of the
analytical instruments are shown in Figures III and IV
respectively.
4.4.3 Findings
The two shortlisted adsorbents (A and B) were subjected to
'raw' condensate feedstock, and the adsorbents were able to
lower the Hg concentration in the sample.
It is very important that the free water is removed since it will
interfere with the adsorption process. Water was also
identified to contain Hg compound especially non-reactive
inorganic mercury.
From both sets of trials (doped and undoped with DMM),
adsorbent A indicated better performance in removing
mercury from the 'raw' condensate. Adsorbent A was
recommended to be selected for the Mercury removal system
for raw condensate.
The above results indicated that speciation of the mercury
content is important in evaluating the efficiency of an
adsorbent system. The performance of an adsorbent was
dependent upon the type of adsorbent, the mercury species and
other impurities present in the feed stream. The determination
of total mercury only in feed and product samples in the
system will provide information on the performance of the
adsorbent but will not give all the necessary information for an
unbiased evaluation to be made of the performance of an
adsorbent.
The percentage of removal efficiency of adsorbents for the
experiment is summarised in Figures V & VI and the example
of chromatogram for the species analysis is shown in Figure
VII.
5.0 Project Execution
5.1 Project Execution Plan
The PCSB gas fields and gas infrastructures supply a
significant amount to Peninsular Malaysia's gas demand. It is
imperative to ensure that this project does not disrupt the
continuous gas supply to consumers. The main objective and
driver for the Projects are HSE and Schedule. A normal
schedule for a project of this size is about 24 months from
inception. With a commencement date of January 2005, the
current forecasted project completion date would be December
2006. However, due to the criticality of the subject matter, the
PCSB Management had requested the Project team to
complete the first unit by the end of the 1st Quarter, 2006
(expedited by 9 months) (33). In order to meet this, a different
approach was taken by the project.
- Contracting Strategy
Maximum parallel engineering, procurement and
construction can be best realized through EPCC
contracting where the interfacing and coordination
works among the various contractors/parties can be
minimized. It also provided a single point direction in
the management of those works thereby enabling
earlier commencement of site works. An EPCC
Contract was executed consisting of the technology
subject expert (PRSS and the technology provider),
the detailed design consultant and the construction,
installation and commissioning contractor.
- Material Sourcing
The project completion date is dictated, to some
extent by the critical path. The critical path for the
Project is the supply of the Mercury Removal unit. In
order to expedite the schedule, the pre procurement
and sourcing processes were conducted by the project
team prior to the award of the EPCC contract to the
EPCC Consortium
5.2 Project Development
The Mercury Removal Project I (MRP I) development was
carried out in two phases:-
Project Definition (EPCC Pre Award Works)
- Data Analysis
- Technology Selection
- Lab Adsorbent Performance Test
- Front End Engineering Design (FEED)
- Basic Design of the Mercury Removal System
Phase 1 - Installation of MRU for JDS
- Commenced the engineering, fabrication and
installation of JDS MRU
- Commenced on the engineering and pre-fabrication
of RDS MRU
- Monitoring Period
Conducted a 6-month monitoring period after the
completion of the Phase JDS MRU. This enabled
data gathering on the MRU performance for lessons
learnt and improvement on the RDS MRU.
Phase 2 - Installation of MRU for RDS
- The detailed designs were revisited taking into
consideration of the lessons learnt from the JDS
MRU.
- Installation of the RDS MRU
- Monitoring Period for the RDS MRU.
6.0 Performance Monitoring
The Mercury Removal Unit for the JDS and RDS were
installed on 31st March 2006 and 30th July 2006, ahead of the
planned schedule. Performance Monitoring Period was
conducted for both of the systems to ascertain the system
performance. The Mercury Removal Unit for both of the
system managed to successfully remove mercury from the raw
condensate to below the sales gas specifications and the
project target, with more than 95% efficiency (37). Figures
VIII and IX show the mercury removal performance for both
the JDS and RDS Mercury Removal System.
7.0 Conclusion
The mercury removal from raw condensate project shows how
the PETRONAS Group had adopted an integrated approach to
effectively address mercury in its gas supply thus ensuring that
not only does its products conform or even exceed
specifications, but demonstrates the Group's commitment to
sustainable development and good environment management
through technology application.
Mercury mapping, speciation study and adsorbent
performance analysis are key activities and capabilities that
ensure the right technology was narrowed down and selected.
Being among the first mercury removal projects for raw
condensate application, this project provides the baseline
experience in the development of skill and capability in the
area of mercury mitigation for PETRONAS group and the
E&P Industry.
8.0 Acknowledgement
We would like to thank PETRONAS and PCSB Management
for their support and approval for us to publish this paper.
References
- Leeper, J. E., "Mercury Corrosion in LNG Plant",
Energy Processing/Canada, Jan-Feb 1981, 46-51.
- Haselden, G.G., "The Challange of LNG in the
1980's ", Mech. Eng., March 1981, 103, 46 - 53.
- Bodle, W.W., Attari, A., and Serauskas, R.
"Considerations for Mercury in LNG Operations",
Inst. of Gas Tech., 6th. Int. Conference on LNG,
Kyoto Japan, Paper 1, April 1980.
- Bigham, M.D., " Field Detection and Implications of
Mercury in Natural Gas", SPE Prod. Eng., May 1990,
120-124.
- Frech, W., Baxter, D.C., Dyvik, G., and Dybdahl, B.,
J. Anal. At. Spectrom., Oct 1995, 10, 769.
- Schickling, C., and Broekaert, J. A. C., Appl.
Organomet. Chem., 1995, 9, 29.
- Leeper, J. E., "Mercury Corrosion in LNG Plant",
Energy Processing/Canada, Jan-Feb 1981, 46-51.
- Leeper, J. E., " Mercury - LNG Problem ", Hydroc.
Proccs., Nov. 1980.
- Cameron, C.J. Didilion, B., Benayoun, D., and
Dorbon, M.," Mercury; A Trace Contaminant in
Natural Gas and Natural Gas Liquids", Eurogas 96,
June 1996.
- Situmorang, M.S.M., and Muchlis, M., " Mercury
Problems in The Arun LNG Plant", 8th. International
Conference on LNG, Los Angeles, June 1986,
session 2, paper 5.
- Shigemura, Y., Hasegawa, T., Cameron, C. J.,
Sarrazin, P., Barthel, Y., and Courty, P., 3rd.
International Petrochemical Conference, Sept. 1991,
Singapore.
- Cameron, C.J. Barthel, Y., and Sarrazin, P., 73rd.
Annual Convention of the Gas Process. Assoc., 1994,
New Orleans.
- Shafawi, A., Abd Hamid, H., " Mercury Removal
from Malaysian Natural Gas", Petronas project report
No. 203, Unpublished.
- Kayat, Z., Miskon, S., and Ali, A.R., "Design
Consideration for Mercury Removal System", Nada
Petronas, 1994, Unpublished.
- Bogani, F., 10th. International Conference on LNG,
paper 4, session 2, May 1992, Kuala Lumpur.
- Reid, J.A., and McPhaul, D.R., 8th. Annual Ethylene
Producer Conference, American Institute of Chemical
Engineering (AICE) Spring National Meeting, paper
21c, 1996, New Orleans.
- Torconis, B., and Jimerez, A., 75th. Annual
Convention of the Gas Processor Association, 1996,
Denver, Pre-print.
- Lund, D.,Oil and Gas Journal, May 1996, 70.
- Anon, Oil and Gas Journal, May 1996, 76.
- Frenken, P.,and Hubbers, T., American Inst. of
Chemical. Eng. Spring National Meeting, proceeding
- English, J.J.,American Inst. of Chemical. Eng., Spring
- Affrossman,S., and Paton, "Interaction of Mercury
with Pt and Pd surfaces", J. Soc. Chem. Ind.
(London), Monograph 28, 1968, 151.
- Wilhelm, S.M., and McArthur, A., "Removal and
Treatment of Mercury Contamination at Gas
Processing Plant", Soc. of Pet. Eng., (SPE No.
29721).
- Frech, W., Baxter, D.C., Bakke,B., Snell, J.P., and
Thommassen, Y., Anal. Comm., 1996, 33 , 7H-9H.
- Snell, J.P., Frech, W.,and Thommassen, Y., Analyst,
1996, 121, 1055.
- Sarzanini, C., Sacchero, G., Aceto, M., Abollino, O.,
and Mestasti, E., Anal. Chim. Acta, 1994, 284, 661-7.
- "Determination of Mercury in Naphtha", UOP
Method 938-95,UOP, 1995.
- Shafawi, A., Foulkes, M. E., Ebdon, L., Corns, W. T.,
and Stockwell, P. B., Analyst,. Analyst, 1999,
124.185-189
- Tao, H., Murakami, T., Tominaga, M, and Miyazaki,
A., J. Anal, Atom. Spectrom., 1998, 13, 1085-1093.
- Shafawi, A., et.al.,"Preliminary evaluation of
adsorbent-based mercury removal systems for gas
condensate"; Anal.Chim. Acta, 415(1-2), June
2000,21-23
- Sarrazin, P., Cameron, C., Barthel, Y, and Morrison,
M.E., American Inst. of Chem. Eng. Spring Meeting,
New Orleans, March 1992, Proceeding 86 a.
- Goto, T., Furuta, A., and Sato, K., JGC Corporation,
Chiyoda-ku, Japan, Technical Letter, Unpublished.
- Mohamed, A.J, " Mercury Removal Project 1 Project
Execution Plan and Contracting Strategy", Petronas
project paper , Feb. 2005, Unpublished.
- Mohamed, A.J., "Mercury Removal Project 1 Project
Brief to PGB ", April 2005, Unpublished
- Sainal, M.R., "Mercury Removal Project 1", Petronas
Project Paper, May 2005, Unpublished.
- Sainal, M.R., Shafawi, A., "Mercury Removal Project
1 - Project Progress Update", Petronas Project Paper,
Nov. 2005, Unpublished.
- Sainal, M.R., "Progress Update on Mercury Removal
Project", Petronas Project Paper, July 2005,
Unpublished.
 |